From: route@monster.com
Sent: Thursday, April 07, 2016 11:50 AM
To: hg@apeironinc.com
Subject: Please review this candidate for: p6 Scheduler
This resume has been forwarded to
you at the request of Monster User xapeix03
|
|||||||
|
|||||||
|
|
|
||||||
|
||||||
|
Alberto Martinez PO Box 1721
● Monrovia, CA 91017●
(626) 827-0314●
amartinez794@yahoo.com HIGHLIGHTS
OF QUALIFICATIONS
· Accountable, responsible, and determined · Construction Claims Analyst for a national construction
claims/litigation consulting firm · Construction Scheduler and Project-Field Engineer for a
construction company building Type V Housing and numerous Proposition O
Projects for the City of Los Angeles · Knowledge in government contracting and procurement with
relevant courses in Contract Administration, Contract Cost/Price
Techniques-Negotiation, Contract Case Study/Practical Application, and
Contract Aspects of the Uniform Commercial Code · Computer skills include: Primavera Project Planner
(P6 & P3), Suretrak Project Planner, MS Word, Excel, PowerPoint, various
litigations databases, and Internet research · Outstanding rapport with clients, consultants, and
co-workers · Active member in the Association for the Advancement of
Cost Engineering International (AACE International), Southern California
Chapter · Active member of Construction Management Association of
America (CMAA) · Willing and eager to learn and take on new challenges · Beta Gamma Sigma Graduate and Member · Bilingual (English and Spanish) · Honorable Discharge from the United States Marine Corps · Experience in field-related scheduling and/or construction
management experience · Works well independently or in a team setting EDUCATION
University of La Verne, La Verne,
CA
March 2014 Master’s in Business
Administration
Emphasis in Management and Leadership
California State Polytechnic University, Pomona
CA
March
2006
Bachelor of Science in Business Administration – Finance, Real Estate, Law
Emphasis in Contract Management United
States Marine Corps
May 1998 Military
Occupation Specialty – Personnel/Administration
PROFESSIONAL
EXPERIENCE
Arcadis ,
Los Angeles
CA
May 2010 –
Present
Construction
Scheduler · Lead or assist in the development of project plan and
schedule in P6. · Lead or assist in the development of functional P6
schedules for engineering, procurement, construction and startup activities. · Assist with the coordination, reconciliation and
integration of functional schedules to create the project control schedule. · Build detailed engineering, construction, and validation
logic driven/resource loaded schedules, analyze critical path updates,
schedule progress, evaluate schedule options, and communicate schedule status
to the project manager, client, consultants and others. · Build detailed engineering cost reports, change notices
and other cost control tools. · Responsible for maintaining project schedule(s) and
alerting project team to potential problem areas. · Collect performance data including installed quantities,
expended labor hours, and other progress measurements for direct hire and
subcontracted work. · Provide periodic checks on bulk material quantities, as
appropriate. · Maintain and update scope within work breakdown structure. · Verify and analyze that scope of work is being planned
according to the Critical Path Method. Optimus
Construction, Glendale
CA
September 2008 – September 2009 Assistant
Project Manager/Project-Field Engineer/Construction Scheduler · Acted as a liaison between the owners, architects,
engineers, inspectors, and subcontractors. · Created and administered construction documents, RFI’s,
and scheduling systems efficiently. · Assisted the project manager with document control and
maintained project logs and technical records. · Conveyed scope of work changes to all trades and parties. · Managed and monitored guidelines for Quality Assurance/Control
according to GC’s Quality Assurance/Control Program, Engineering, and Design
Requirements. · Attended, participated, and produced effective project
team meeting minutes by documenting issues and solutions that arose,
including developing a critical action items list. · Communicated with Architects, Engineers and City Officials
to develop solutions to design issues. · Supported project superintendent with field coordination,
issues, and solutions. · Facilitated the resolution of everyday challenges on a
construction job site. · Accountable for the development and maintenance of
construction schedules for all of the company’s current and future projects. · Responsible for creating and reviewing project baselines. · Monitored and tracked construction schedule progress. · Provided and presented periodic look-ahead schedules with
current progress and forecasted completions. Arcadis
(PinnacleOne), Los Angeles
CA
May 2006 – August
2008
Construction
Claims
Analyst
· Examined, reviewed, and evaluated data for a national
construction claims/litigation consulting firm. · Accountable for the maintenance of litigation documents in
various formats. · Analyzed construction claims for merit and entitlement. · Evaluated construction schedules for reliability and
integrity. · Prepared issue briefs. · Examined construction claim issues submitted by claimants. · Utilized scheduling software to evaluate construction
delays. · Conducted research and document management in support of
construction claims analysis and expert testimony by others. · Provided technical support to team members and to client
counsel. PROJECTS
Wilmington Drain Multi-Use Project, City of Los Angeles Prop O Clean
Water Program, Harbor City, CA May
2013 to Present, $16 Million Project
is in the first phase of the Machado Lake Integrated Water Quality and
Habitat Improvement Program. It includes grading of approximately 3,250
feet of soft bottom channel with varying widths, which has vegetation growth
and sediment accumulation. There will be a construction of a 20’
wide, 115‘long and 10’ high 4’ high CIP trash net structure at the
north end of the channel; 200 linear feet of CIP retaining walls, varying
from 15 to 25’ high along the edges of the channel, turf reinforcement mat
below the daylight line on all the disturbed slope for scour prevention and
erosion control, improvements of the existing maintenance road, new pathway,
entries, native vegetation landscaping, use of bio filters or similar
vegetated BMP, creation of a recreation area by replacing bare soil with
parkland, and channel re-contouring and alignment. Scheduler
for various projects and tasks include coordinating submittals, ensuring that
the work is within the all the contract documents, reviewing and analyzing
construction schedules and ensuring they are developed according to the
critical path method, preparing comments to the monthly schedules submitted
making sure they are within contract duration and performing schedule
estimates, reviewing construction progress, attending weekly construction
meetings, performing Time Impact Analysis and delay analysis, if needed, and
supporting the CM team tasks in a team environment. Temescal
Canyon Water Quality Improvement Phase I, City of Los Angeles Prop O Clean
Water Program, Pacific Palisades, CA August
2011 to May 2013, $9 Million This project diverts runoff from the storm drain
in the Temescal Canyon road through a hydrodynamic separator for storage in
an underground detention tank in the Temescal Canyon Park. Subsequent
disposal occurs through a sanitary sewer for further treatment at the
Hyperion Treatment Plant. The major components consist of a storm water
diversion structure, dry weather return diversion structure, hydrodynamic
separator, discharge pump and valve structure, and force main
rehabilitation. The discharge pump is 24x12x30 and has two (2)
submersible pumps that are 25HP each. The discharge of the storm water
will be into a 16” DIP force main into the sanitary sewer once it has been
stored in the underground tank for more than 72 hours after a major storm
event has occurred. The end result of the project is to achieve
compliance with the Santa Monica Bay Beaches Wet Weather Bacteria Total
Maximum Daily Load (TMDL) regulations. In addition to the water quality
components, this project incorporates recreational benefits for the community
with a new playground and new bathroom facilities. Lead Scheduler for the project and tasks included
supporting the Construction Management Team with change order negotiation
including any impact evaluations, submittal coordination, schedule risk, coordinating
among several agencies regarding permits, reviewing and analyzing
construction schedules ensuring they are planned using the Critical Path
Method, preparing comments to the monthly schedules submitted, confirming
schedule estimates, reviewing construction progress, attending weekly
construction meetings, and performing Time Impact Analysis (TIA) for the
differing site conditions events experienced on the project and presenting
finding to upper management. Involved in coordinating change of scope work
with the subcontractors and ensured buy-in from the end user. Once the
project has completed on site testing, will be responsible for closing out
the project. This involves ensuring that the instrumentation integration from
the project site to the Venice Pump Station is completed according to the
plans and buy-in from the end user. Will coordinate with phone utility
companies, subcontractors, general contractor, and several City of Los Angles
departments to ensure project completion and proper project turnover. Albion
Dairy Industrial Facility Demolition & Remediation, City of Los Angeles
Prop O Clean Water Program, Los Angeles, CA July
2011 to June 2013, $4.1 Million This project involves demolition of the buildings
and improvements of an industrial facility, remediation and abatement of all
hazardous materials and soils onsite, and the importation of clean soil, as
required; to leave the property in a level graded condition for the future
development of a Proposition O Project. Lead Scheduler for the project and tasks included
reviewing and analyzing construction schedules and confirming that it was
planned and updated using the Critical Path Method, preparing comments to the
monthly schedules submitted, reviewing construction progress and verifying
construction estimates and risks, attending weekly construction meetings and
reporting and advising on progress concerns, and performing TIA and delay
analysis and supporting the CM team in a team setting. Penmar
Water Quality Improvement Phase I, City of Los Angeles Prop O Clean Water
Program, Venice, CA November
2010 to July 2013, $12 Million The first phase of the project was designed to
direct a portion of the area’s dry-weather urban runoff and wet weather storm
water to the Hyperion Treatment Plant for pollutant removal. The end
result of the project is designed to treat up to three million gallons (per
storm event) of storm water from the watershed that is currently untreated
which drains and flows into the Santa Monica Bay. The major components
consist of a storm water diversion structure and two Pump Stations with a
total of 8 pumps. The larger Pump Station was 20x60x25 with 6 pumps.
Four (4) of the pumps were submersible with constant speeds each with 30
HP. The other 2 pumps were 15 HP with variable speed and were used
during the low flow periods. During the wet weather season the pumps
will be used to discharge to the Reservoir tank to keep for storage for 72
hours. Other components of the work included a dry weather
return diversion structure, pump station at the Reservoir tank, discharge
pumps and valve structure, 30’ DIP and 12” DIP force mains and a 3 MG
underground storage tank. The tank was a DYK post tension tank that
needed a deep shoring installation system that was 300 plus linear feet and
was supported by soil nail tie-back method. The Reservoir pump station
has 2 pumps that were 20 HP submersible and had variable speeds and
discharged into the sanitary sewer. A portion of the work near
the tank included microtunneling for the main 48” tank discharge line.
In addition to the water quality components, this project will incorporate
recreational benefits for the community where it will provide a new playing
field for the community. Served as the Scheduler for the project and
worked with the GC to obtain permits from City agencies, Building and Safety,
and Department of Water and Power in order to energize the main switch gear
on schedule. This involved submittal coordination, reviewing and analyzing construction
schedules and making sure baseline and updates were planned according to the
Critical Path Method, preparing comments to the monthly schedules submitted,
reviewing construction progress, creating and tracking subcontractor
schedules, attending weekly construction meetings, reviewed schedule
estimates, schedule risk, performing TIA and delay analysis, when needed, and
presenting findings to Owners/General Contractor representatives, supporting
the CM team during change order negotiations with the General Contractor in a
team setting. In addition was responsible for coordinating the
instrumentation integration from the project site to the Venice Pump Station
(commissioning activities). Served as the Construction Manager, which
involved coordination with the various utility phone companies, Bureau of
Sanitation, Arcadis PLC Programmers, and subcontractors out in the
field. Within the scope of work, ensured that Pump Stations were
working in accordance to the plans and working according to the scope of work
in order to turn over the completed project to the client. In addition,
made certain that there was buy-in from the client and the needs were
satisfied. Westside Park Rainwater Irrigation, City of Los Angeles Prop O Clean
Water Program, Los Angeles, CA May
2010 to July 2012, $3 Million This project diverts dry–weather urban run-off
from an existing storm drain for treatment through a floatable screening well
and influent pump station at the project site. The influent pump
station has 2 submersible non-clog wastewater pumps that are 3.8 HP and pumps
the stormwater through a pre-cast valve vault, metering vault, and
underground irrigation piping. The runoff will be distributed to turf
areas via a subsurface irrigation system. Excess subsurface irrigation
water will flow into a dry creek with a perforated pipe and back to the storm
drain. In addition to the water quality components, this project will
incorporate recreational benefits for the community. Recreational
features will include new perimeter fencing, jogging paths, and a sensory
garden, as extension of the dry creek. Served as the Scheduler and ensured the
electrical work was planned according to schedule and there was coordination
among the Department of Water and Power, Building and Safety, and the General
Contractor. Lead on reviewing and analyzing construction schedules and make
certain the work was planned according to the Critical Path Method, preparing
comments to the monthly schedules submitted and presented finding to
Construction Management Team, reviewing construction progress, evaluated
schedule estimates and risks, attending weekly construction meetings,
performing TIA and delay analysis, if needed, and supporting the CM team in a
team setting. In addition, was responsible for coordinating the
instrumentation integration from the project site to the Venice Pump Station
(commissioning activities). Served as the Construction Manager, which
involved coordination with the various utility phone companies, Bureau of
Sanitation, Arcadis PLC Programmers, and subcontractors out in the
field. Within the scope of work, ensured that Pump Stations were
working in accordance to the plans and working according to the scope of work
in order to turnover the completed project to the end user. In
addition, made certain that there was buy-in from the client and the needs
were satisfied. Peck
Park Enhancement, City of Los Angeles Prop O Clean Water Program, San Pedro,
CA May
2010 to October 2011, $4 Million Project consists of the installation of vegetated
bio-swales, infiltration strips, stormwater catch basins, armoring and
re-vegetation for bank stabilization, and a step-pool channel in Peck
Park. A portion of the work included several storm drain pipelines
throughout the project site with cast in place anchors. Acted as the Assistant CM / Scheduler for the
project and tasks included submittal coordination, change order negotiation,
inspection of work, reviewing and analyzing construction schedules, made
certain work was planned according to the Critical Path Method, preparing
comments to the monthly schedules submitted and presenting findings to the
team, reviewing construction progress, verified schedule estimates and risks,
attending weekly construction meetings, performing TIA and delay analysis, if
needed, and supporting the CM team. Coordinated and worked closely with the
GC and subcontractors in order to create and recommend alternative courses of
actions on meeting critical construction milestones and reported and advised
the Project and Construction Manager on the outcomes of the proposed
actions. During post-construction, in charge of working with
subcontractor and client to coordinate habitat restoration activities and
ensuring the project meets the California Regional Water Quality Control
Board compensatory mitigation report. SCADA
Instrument Integration for Proposition “O” Projects Mar Vista Recreation
Center Stormwater BMP, Proposition O Project South Los Angeles
Wetlands, Proposition O Project Downtown Low Flow
Diversion, Proposition O Project Santa Monica Low Flow
Diversion #4, Proposition O Project Helped in coordination with the instrumentation
integration from the project site to the Venice Pump Station. Worked
occurred during the post-construction phase and work had been completed for a
significant amount of time. Served as the Construction Manager and was
responsible for coordination with the various utility phone companies, Bureau
of Sanitation. Arcadis PLC Programmers, and subcontractors out in the
field. Within the scope of work, Ensured that the Pump Stations were
working in accordance to the plans and working according to the scope of work
in order to turn over the completed project to the client. In addition,
made certain that there was buy-in from the client and the needs were
satisfied. Cantabria & Asturias Senior Apartments – Van Nuys, CA Meta Housing contracted Optimus Construction to build a 92,000 sq. ft.
and 88, 000 sq. ft. Type V senior apartment complex. The three-story
wood framed buildings sat on a podium deck above various levels of on grade
and underground parking. The combined cost of the projects was $30.75
million dollars and included: 150 units, enclosed courtyard with water
features, outdoor fireplace and barbeques, outdoor recreation area, art
studio, and community room. I prepared and maintained schedules,
reviewed project baselines, monitored and tracked progress, and provided
periodic look-ahead schedules utilizing Suretrak Project Planner software. Andalucía Senior Apartments – Van Nuys, CA Meta Housing contracted Optimus Construction to build a 381,000 sq.
ft. Type V senior apartment complex. The four-story wood framed
building sat on semi-subterranean parking structure. The cost of the
project was $22 million and included: 94 units, above ground spa with
overhead trellis, open courtyard with fountain, planters, sitting areas,
outdoor fireplace, recreation room with library and computer rooms, community
room with kitchen, gas barbeques, and secured access. I prepared and
maintained schedules, created and reviewed project baselines, monitored and
tracked progress, and provided periodic look-ahead schedules utilizing
Suretrak Project Planner software. In addition, I also served as the
project engineer and was involved in every facet of the daily activities of
the project. Cedars-Sinai Health System/Cedars Central Plant – Los Angeles, CA PinnacleOne was brought to review and analyze agreements, documents,
performance of contracts, and claims related to the new CSHS Saperstein
Critical Care Tower Project. My tasks included review and analysis of
delay to the project and creation of graphics to be used in resolution of the
disputes. I also researched and analyzed documents regarding changes in
the Central Plant in preparation of further proceedings. Clark County Regional Justice Center – Las Vegas, NV PinnacleOne was retained to provide damage analyses and expert
testimony for the $68 million claim submitted by AF Construction on the Clark
County Regional Justice Center. The new courthouse houses the District,
Justice, Municipal and Supreme Courts. The Contractor was terminated
for default and PinnacleOne’s analysis included both an assessment of the value
of the Contractor’s claim and itemization of damages sought by Clark
County. My role included the review and analysis of the Contractor’s
and Subcontractor’s claim and collection of exhibits to determine entitlement
on the Contractor’s claimed damages. Port of Los Angeles Harbor Force Main and Siphon Relocation Project
Claim – San Pedro, CA Westcon was retained by the Port of Los Angeles (POLA) to relocate and
remove a 30' sewer force main crossing that spawns 1,600 feet under the main
channel in Los Angeles Harbor to accommodate POLA’s channel deepening
project. Westcon experienced multiple tunneling shaft collapses and
ultimately finished the project 950 days late. My responsibilities on
behalf of the POLA included analyzing and researching documentation for the
various issues claimed by the contractor pertaining to project delays. City of Anaheim Tustin Avenue Bridge Widening – Anaheim, CA The City of Anaheim received a claim from the contractor on a bridge
widening project where the contractor alleged various damages that included
project delay, additional survey work, changes to median barrier rail, and
late payment issues. PinnacleOne was retained to analyze project
documents and determine the extent of the delays and the responsible party
for the purpose of assisting the City of Anaheim with potential settlement
discussions and mediation. I assisted in reviewing and analyzing all
documents pertaining to the claim and in the creation of graphics that would
aid in settlement discussions at mediation. Metropolitan Transportation Authority/Orange Line – Los Angeles, CA The Metropolitan Transportation Authority retained PinnacleOne to
review the claim brought forth by the contractor on the Orange Line Busway
Project. PinnacleOne analyzed claims related to pavement failures on
the Orange Line Busway. I contributed by reviewing and analyzing the
contract documents, correspondence, and geotechnical reports. Honeywell Street & Queens Boulevard Bridges – New York City, NY The New York City Law Department retained PinnacleOne to provide
Document Management and Issue Coding for a $4.4 million claim brought against
the New York City Department of Transportation. The project consists of
two bridges which span over one of the nation’s largest rail yards. The
contractor’s claim included delay, alleged failure to provide track outages,
extended overhead, differing site conditions, and loss of an incentive
bonus. My role was to assist in the implementation of a complex document
management system. Sprinter Project – Escondido, CA PinnacleOne was contracted by Simon Wong Engineering to provide
Construction and Project Management, project controls and to work alongside
with their team and the North County Transportation Authority for the
development of the Sprinter rail line. The Sprinter Project is a 22
mile rail line that runs along the 78 corridor that is a new link between
Oceanside, Vista, San Marcos, and Escondido. I provided dispute avoidance and
resolution analyses when a claim of $10 million was submitted by the
Contractor. RD Olson Construction, Union Station Village Apartments – Los Angeles,
CA PinnacleOne was retained to provide services on behalf of the
contractor related to disputes arising between RD Olson and the owner/developer
of the project in construction of the 278 unit apartment building at Union
Station. I performed review and assembly of relevant project
documentation for issue brief development and assisted in PinnacleOne’s
independent analysis of schedule delays. My role was to review the
project documents and various issues disputing delay. I created an
issue brief in support of a weather delay claim alleged by the contractor. Cesar Chavez Middle School – Oceanside, CA PinnacleOne was retained to provide Construction Dispute Resolution
services on behalf of the Oceanside Unified School District. The $25
million project was for the construction of a middle school with construction
duration of 22 months. The project ran into substantial delay due to coordination
problems by various parties and the spread of contaminated soil throughout
the jobsite. I assisted in the development of an As-Built Schedule
depicting the importation of the soil. |
|
|
||||||||
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||
|
|